Library Mechanical and Electrical Upgrade
Completion: September 2010 Duration: 3 Months
Procurement: Traditional
The works on Harris Grounds and first floors together with Kirkham 013 are to ensure the provision of next year's teaching of Architecture/BNE.
LIBRARY MECHANICAL AND ELECTRICAL UPGRADE
Completion: 24th September 2010 Duration: 3 Months
Procurement: Traditional
The scheme is a mixed mechanical and electrical upgrade approx £1/m in value. It includes new efficient boilers, upgraded air handling systems and a new electrical mains panel and transformer increasing the buildings electrical capacity.